Bad odour under orders

Landsborough meat plant ordered to tackle ongoing odour complaints

By Sonia Isaacs

A LANDSBOROUGH meat rendering plant has been ordered to undertake major upgrades following ongoing complaints about offensive odours affecting nearby residents, with works required to continue into 2028.

Queensland’s Department of the Environment, Tourism, Science and Innovation (DETSI) issued a second Environmental Enforcement Order to Norganic Proteins Pty Ltd on October 16, requiring immediate operational changes and extensive improvements to the facility.

The latest enforcement action follows 22 odour nuisance reports from four complainants between July 8 and August 20, with departmental officers subsequently detecting offensive odours downwind of the facility.

It is understood numerous residents have made odour complaints to the department over the past 12 months.

During inspections on September 8, officers identified what they described as a “burnt/smoky cooking odour” affecting nearby properties.

The department alleges the company has breached conditions of its environmental authority, which prohibits emissions causing environmental nuisance.

A DETSI spokesperson confirmed the latest enforcement action followed an earlier order issued in March.

“Norganic Proteins has been issued a second Environment Enforcement Order requiring it to implement recommendations from a qualified expert to reduce nuisance odours affecting the local community,” the spokesperson said.

Under the latest order, Norganic Proteins must immediately improve raw material storage and handling, including covering outdoor materials, using chilled storage for high-odour feedstocks and keeping processing areas enclosed.

Independent environmental specialists were required to be appointed by October 30, with temporary odour containment measures due by November 30.

Repairs to the facility’s covered anaerobic lagoon system must be completed by January 30, 2027.

More substantial upgrades will follow, including fully enclosing the rendering building and installing controlled negative-pressure ventilation by March 2028.

Wastewater treatment upgrades must be completed by June 2028.

DETSI stated the company had failed to take all reasonable and practicable measures to prevent or minimise environmental harm from continuing odour emissions.

Failure to comply with the order without reasonable excuse constitutes an offence under Queensland’s Environmental Protection Act 1994, carrying potentially significant penalties.

Sunshine Coast Council confirmed it had received two odour complaints concerning the facility over the past 12 months, referring both to DETSI for investigation.

A council spokesperson said responsibility for regulating odour emissions rested with the State Government.

“While Council works closely with DETSI and participates in joint investigations where appropriate, responsibility for regulating odour emissions at this site rests with the State Government,” the spokesperson said.

“The development approvals and conditions regulated by Council over this site do not contain conditions relating to odour.”

The facility processes animal by-products and has operated in Landsborough for several decades, providing services to regional meat and seafood industries.

Norganic Proteins owner Kent Quinn has previously said the company was working with DETSI and industry experts to address odour issues at the facility.

Norganic Proteins was approached for comment on the latest enforcement order.

Advertisement