‘Deep frustration’ with council over two year delay as opponents prepare to battle
By Sonia Isaacs and Mitch Gaynor
HANSON has hauled Sunshine Coast Council into court after its bid to more than double output from the controversial Glass House Mountains Quarry stalled in planning limbo.
The long-running and contentious application, first lodged two years ago, seeks to lift the quarry’s extraction cap from 600,000 tonnes to 1.2 million tonnes a year.
The proposal also includes extending operating hours, deepening the pits, and shifting processing operations on site. While both parties had previously agreed to extend the decision period, the statutory timeframe expired in August. Hanson treated this as a deemed refusal and lodged an appeal in the Planning and Environment Court.
Explaining the decision to appeal, a Hanson spokesperson said the development application, lodged on 27 July 2023, was properly made and supported by a comprehensive assessment. The proposal included $5 million in upgrades to six intersections and 1.6 km of the transport route, alongside existing and additional pavement maintenance contributions.
“We are deeply frustrated and disappointed with the timeframe it has taken the Sunshine Coast Council to assess our development application for the existing quarry at Glasshouse Mountains,” the spokesperson said.
“The continued delays associated with the assessment of the application are preventing us from committing to supply an additional 600,000 tonne per annum to support the Sunshine Coast region.
“If the available supply does not meet demand, then the price of construction materials on the Sunshine Coast will continue to increase, as will the cost of housing construction and development.
“If the cost of housing construction and development increases, the housing crisis will not only continue but will intensify.”
The spokesperson added that key infrastructure projects that are planned to support the growth of the Sunshine Coast, such as the direct Sunshine Coast rail line, would be at risk of a reduction in project scope or cancellation of funding as the cost of construction material escalates due to restricted supply of materials.”
The spokesperson said that Hanson had provided extensive scientific responses “backed by data, to address all concerns raised by Council” and the company had agreed to three extensions of time over the past six months since the application entered the decision-making period in February 2025.
“Council has had more than two years to assess the application, and it has become evident that the matter has seen minimal progress in recent times. Under the Planning Act 2016, applicants may lodge a deemed refusal if an impact-assessable application is not decided within the legislated timeframe.
A Sunshine Coast Council spokesperson said that it had agreed to multiple extensions and it was Hanson’s own decision to commence court action before a decision was made by council.
“Council and the applicant had previously agreed to multiple extensions of the decision period,” the spokesperson said.
“However, the applicant declined to extend beyond August 8 2025 and lodged a deemed refusal before Council could make a decision. As a result, the Court is now the assessment manager.”
In its notice of appeal, filed on Monday, September 1, Hanson argued that the land was already zoned for extractive industry under the state’s planning framework and was identified as a Key Resource Area (KRA), earmarked for its hard rock reserves.
The company stated that the expansion complies with all relevant planning instruments and benchmarks and should be approved.
Hanson also stressed that the site had long been recognised under earlier planning consents, including a 1999 permit. The company contended the expansion was essential to meeting demand for construction materials across South East Queensland, while maintaining the existing truck haulage route via Coonowrin Road and the Steve Irwin Way.
The proposed expansion had sparked strong opposition from the community, led by the Save Our Glass House Mountains (SOGHM) group. Critics warn of increased traffic, dust, and noise, while arguing the expansion threatens the scenic landscape that underpins the region’s tourism economy.
Hundreds of submissions were received during the public notification period last year, with many raising concerns about heavy vehicle movements through the township and the quarry’s proximity to the heritage-listed mountains.
SOGHM spokesperson Megan Standring said: “It’s really disappointing, because it feels like it just sidesteps the decision process.
“We’re not sure where Council stands, so we’re hoping that they’re going to support their community with all the evidence that’s been submitted to them over the duration of these two years.”
Glass House Mountains resident and SOGHM member, Burnice Starkey added: “It appears the Heidelberg Materials realised that SOGHM and the community were gaining traction.”
“This is a strategic move in an attempt to preempt the Council rejecting their application.
“Since we anticipated that this would probably go to appeal, the procedure isn’t a surprise. However it does show the disrespect this company has for the Sunshine Coast Council and this community.”
Division 1 Councillor Jenny Broderick defended the Council’s handling of the matter, saying Council had been actively and thoroughly assessing the development application.
“You can see the extensive correspondence on Development-i. It’s a complex and technical proposal – well beyond a standard shed approval and our planners have been diligent throughout.”
Cr Broderick said Council and Hanson had maintained regular communication throughout the process with further information provided from Hanson in only recent weeks.
“While both parties had previously agreed to extend the decision period, so that appropriate due diligence could be undertaken, the applicant chose not to extend beyond August 8 2025 and lodged a deemed refusal with the Planning and Environment Court,” she said.
Cr Broderick also noted the rights of submitters: “I understand anybody who did have a properly made submission will have a right to appeal. They will receive their letters from the lawyers, and they will then have the opportunity to join in an appeal.”
The application was publicly notified from April 9 to May 2 2024, attracting 528 submissions, 488 of which were properly made.
Submitters who made valid submissions will be notified of the appeal and may elect to become formal parties to the appeal within 10 business days. Further information is available on Council’s website or the Planning and Environment Court.
Member for Glass House, Andrew Powell, was contacted by GC&M News but declined to comment, as he said the matter was now before the courts.
With legal proceedings now underway, the Sunshine Coast community watches closely as the court weighs industrial development against environmental and local interests in one of the region’s most iconic landscapes.
Tell us your thoughts at editorial@gcnews.com.au